Views: 2 Author: Site Editor Publish Time: 2018-11-12 Origin: Site
Welcome the delegates from IEFCL for the progress review of ASU3 project!
October, 21st, 2018, Mr. Anand K Gupta and Mr. S Murali Mohan made the visit to our office in Suzhou for the progress review of the ASU 3 Project.
The ASU 3 project was activated from August 17th, 2018 which is one LSTK project with supply of one unit of cryogenic nitrogen plant with output of gaseous nitrogen at 5200Nm3/hr (Max), which includes the superior supply of FS-Elliott make feed air centrifugal compressor, SOPC make cold box as well as two units of cryogenic liquid nitrogen storage tank for backup. The unit will be designed with latest process at highest effeciency and stability. Highest automatibility with function of remote control to make the plant smart operation. PDS Programme applied for the 3D modeling of the unit to make sure the precise connection for field construction.
The unit is foreseen to deliver to the site for erection & installation by end of April, 2019.